期刊文献+

土压平衡式盾构机富水砂层施工的沉降分析及对策 被引量:4

Settlement Analysis for Construction of EPB Shield Machine in Water-rich Sand Layer and the Countermeasures
下载PDF
导出
摘要 依托土压平衡式盾构机在富水砂层中的施工实例,结合盾构机的工作原理和结构特点,总结盾构机在富水砂层中施工时的沉降规律,分析各阶段地面沉降的原因,有针对性的采取沉降控制措施,利用信息化施工手段,有效控制地面沉降。 In this paper, based on construction case of EPB Shield Machine in the water-rich sand layer, combining with the working principle and structure characteristics of the shield machine, the settlement taws during the construction of EPB Shield Machine in water-rich sand layer is summarized. According to the cause analysis of ground settlement in different stages, the targeted settlement control measures are suggested, Measures of informationization construction are used to effectively control the ground settlement.
作者 赵守宪
出处 《铁道技术监督》 2014年第9期35-38,共4页 Railway Quality Control
关键词 土压平衡式盾构机 富水砂层 沉降控制 Earth Pressure Balanced Shield Machine Water-rich Sand Layer Settlement Control
  • 相关文献

参考文献3

  • 1杜文库,王海,闫和永.北京地铁五号线盾构试验段工程施工综述,地下铁道新技术文集[C].成都:西南交通大学出版社,2003:486-491.
  • 2杨秀权,李孝荣.土压平衡盾构在广州地铁中的应用,地下铁道新技术文集[C].成都:西南交通大学出版社,2003:434-439.
  • 3乐贵平,贺少辉,罗富荣,等.北京地铁盾构隧道技术[M].北京:人民交通出版社,2012:598.