Fuzzy Flexible Resource Constrained Project Scheduling Based on Genetic Algorithm 被引量:1

Fuzzy Flexible Resource Constrained Project Scheduling Based on Genetic Algorithm
下载PDF
导出
摘要 Both fuzzy temporal constraint and flexible resource constraint are considered in project scheduling. In order to obtain an optimal schedule, we propose a genetic algorithm integrated with concepts on fuzzy set theory as well as specialized coding and decoding mechanism. An example demonstrates that the proposed approach can assist the project managers to obtain the optimal schedule effectively and make the correct decision on skill training before a project begins. Both fuzzy temporal constraint and flexible resource constraint are considered in project scheduling. In order to obtain an optimal schedule, we propose a genetic algorithm integrated with concepts on fuzzy set theory as well as specialized coding and decoding mechanism. An example demonstrates that the proposed approach can assist the project managers to obtain the optimal schedule effectively and make the correct decision on skill training before a project begins.
作者 查鸿 张连营
出处 《Transactions of Tianjin University》 EI CAS 2014年第6期469-474,共6页 天津大学学报(英文版)
基金 Supported by the National Natural Science Foundation of China(No.71272146)
关键词 project SCHEDULING FUZZINESS FLEXIBILITY GENETIC algorithm TRAINING project scheduling fuzziness flexibility genetic algorithm training
  • 相关文献

参考文献20

  • 1Brucker P, Drexl A, Mohring R et al. Resource-constrainedproject scheduling: Notation, classification, models, andmethods[J]. European Journal of Operational Research,1999, 112(1): 3-41.
  • 2Hartmann S, Briskorn D. A survey of variants andextensions of the resource-constrained project schedulingproblem[J]. European Journal of Operational Research,2010, 207(1): 1-14.
  • 3Kolisch R, Padman R. An integrated survey ofdeterministic project scheduling[J]. Omega, 2001, 29(3):249-272.
  • 4Herroelen W, Leus R. Project scheduling underuncertainty: Survey and research potentials[J]. EuropeanJournal of Operational Research, 2005, 165(2): 289-306.
  • 5Hapke M, Slowinski R. Fuzzy priority heuristics forproject scheduling[J]. Fuzzy Sets and Systems, 1996,83(3): 291-299.
  • 6Bhaskar T, Pal M N, Pal A K. A heuristic method forRCPSP with fuzzy activity times[J]. European Journal ofOperational Research, 2011, 208(1): 57-66.
  • 7Wang J. A fuzzy project scheduling approach to minimizeschedule risk for product development[J]. Fuzzy Sets andSystems, 2002, 127(2): 99-116.
  • 8Wang J. A fuzzy robust scheduling approach for productdevelopment projects[J]. European Journal of OperationalResearch, 2004, 152(1): 180-194.
  • 9Cai X, Li K N. A genetic algorithm for scheduling staff ofmixed skills under multi-criteria[J]. European Journal ofOperational Research, 2000, 125(2): 359-369.
  • 10Yannibelli V, Amandi A. A knowledge-based evolutionaryassistant to software development project scheduling[J].Expert Systems with Applications, 2011, 38(7): 8403-8413.

同被引文献11

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部