期刊文献+

一起110kV升压站越级跳闸事故分析 被引量:1

Analysis on Override Trip in One 110kV Stepup Station
下载PDF
导出
摘要 对一起光伏电站110 kV升压站越级跳闸事故进行了现场调查分析,发现了型号为PST692U的变压器复合电压闭锁(方向)过流保护装置未引入各侧开关合位接点,不能满足保护启动逻辑条件,导致保护闭锁,故障时不能动作。随后根据现场实际情况提出了具体解决方案和整改措施。 Through analysis on the override trip of one 110 kV step-up station for a photovoltaic power plant, it finds that the overcurrent protection devices of the combined voltage blocking (direction) of the transformer (Model:PST692U) are not connected to the closing points of switches on both sides, which cannot satisfy the logic conditions of the protection startup, resulting in the protection blocking and no action when failure occurs. Later, a solution and remedy measures are provided according to the actual conditions at site.
作者 高宁 王小琳
出处 《西北水电》 2014年第5期77-79,共3页 Northwest Hydropower
关键词 电缆 故障 越级跳闸 传动试验 后备保护 electric cable fault override trip transmission test backup protection
  • 相关文献

参考文献3

共引文献21

同被引文献3

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部