在武汉美术馆改造工程中,通过对静压钢管桩封桩工艺进行改进形成了一种凹入式封桩技术,并总结出一套完整的施工工艺,经过检验测定,满足加固改造设计要求及施工质量验收规范要求,成功解决了采用传统封桩技术占用楼层空间的难题。
In the renovation project of Wuhan Museum,a recessed sealing pile technique was formed that by improving the sealing pile technology of jacked steel pipe pile,as summed up a set of complete construction process,through testing,meet the reinforcement design and construction quality acceptance specification requirements,the problem of traditional sealing pile technology occupation of floor space was successfully solved.
出处
《山西建筑》
2014年第33期41-42,共2页
Shanxi Architecture
关键词
静压钢管桩
锚杆桩
封桩技术
基础加固
jacked steel pipe pile
anchor pile
sealing pile technique