摘要
从变电运行管理的倒闸操作和工作许可流程方面出发,探讨了现行制度及实际操作中存在的一些弊端,并对改进策略作了分析,以通过优化流程、加强操作和工作前的准备工作,使变电设备的停电检修工作效率更高,达到减少停电时间和减少现场人员作业时间的目的。
From the switching operation and work permit process of substation operation management, this paper analyzed some defects in current system and actual operation, and analyzed the improvement strategy, so as to through optimizing process, strengthening operation and preparation before work, made the power fail check work efficiency more high of substation equipment, gained the purpose of reducing power fail time and field personnel operating time.
出处
《山西建筑》
2015年第1期244-245,共2页
Shanxi Architecture
关键词
倒闸操作
工作许可
停电检修
效率
switching operation
work permit
power fail check
efficiency