期刊文献+

巴江口水电站施工导流设计及技术特点 被引量:5

Construction diversion design and technical characteristics of Bajiangkou Hydropower Project
下载PDF
导出
摘要 论述了巴江口水电站的施工导流标准与导流方式方法,分析了施工导流设计的技术特点。结合地形条件、施工期通航、工程提前发挥效益、永久与临时建筑物结合等因素,对导流方案进行综合比选,并介绍了最优方案的设计成果。 With regard to construction diversion of Bajiangkou Hydropower Project, the authors analyzed the fiver diversion standard and method as well as the technical characteristics of construction diversion design. Comprehensive comparison of diversion schemes was conducted in respects of topographical conditions, construction-period navigation, benefits, combination between permanent and temporary structures. An introduction was made on the design of the optimum scheme.
出处 《广西水利水电》 2014年第5期90-92,96,共4页 Guangxi Water Resources & Hydropower Engineering
关键词 施工导流 过水围堰 截流 通航 巴江口水电站 Construction diversion overflow cofferdam river closure navigation Bajiangkou Hydropower Project
  • 相关文献

同被引文献13

引证文献5

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部