摘要
胜利东二矿二期工程初步设计首采区采用的是西推方案,该方案基于现采场位置和拉沟长度,由于目前南帮存在断层、弱层等地质构造,按原二期初设西推方案最终无法保证边坡稳定,且南帮还将布置有半连续工艺的胶带运输系统,南帮滑坡将对生产造成了极大的影响。因此,提出了二期首采区西北推与西推方案进行重新比选。
Based on stope position and slotting length, the second phase project preliminarily designs first mining area which adopts westward advance scheme. Owing to south slope existing fault and weak layer, the former westward advance scheme of second phase project cannot ensure slope stability and south slope will layout belt transport system of semi-continuous process. South slope landslide will have great effect on production. Therefore, the article presents the first mining area of second phase project northwest advance scheme and westward advance scheme and carries out re-selection.
出处
《露天采矿技术》
CAS
2014年第10期17-19,24,共4页
Opencast Mining Technology
关键词
首采区
西推方案
西北推方案
V-P曲线
基建量
first mining area
westward advance scheme
northwest advance scheme
V-P curve
capital construction account