黄河苏只水电站泄洪闸消力池底板冲蚀破坏修复 被引量:4

Rehabilitation of bottom slab erosion of stilling basin at Suzhi hydropower station on Yellow River
下载PDF
导出
摘要 苏只水电站泄洪闸消力池底板基础廊道排水管,在电站运行初期就存在排水带泥问题,一直困扰着电站运行,本次水下检查发现消力池底板局部冲磨严重。经研究,采用围堰挡水,抽干消力池,进行全面修复处理。处理方案为:在原设计底板表面整体加厚15 cm,强度等级C35F100W8的硅粉抗冲耐磨混凝土。 This paper gives an introduction on the reparing treatment for erosion wear of the bottom slab of stilling basin for floodgate at Suzhi hydropower station on Yellow River. The problem of water dis- charge with mud and sand exerts adverse influence on the operation of the hydropower station. The re- sult of underwater inspection shows that the severe wear occurred at part of slabs of stilling basin. The conclusion of research is that the complete treatment should be carried out after cleaning the water in stilling basin by use of temporary cofferdam. The treatment is covering the abrasion-resistant siliceous concrete of C35F100W8 on the top of slab, with the thickness of 15 cm.
出处 《大坝与安全》 2014年第5期55-58,共4页 Dam & Safety
关键词 消力池底板 冲蚀破坏 修复 苏只水电站 bottom slab of stilling basin erosion wear defect repairing Suzhi hydropower station
  • 相关文献

参考文献2

  • 1孙志恒,夏世法,付颖千,甄理.单组分聚脲在水利水电工程中的应用[J].水利水电技术,2009,40(1):71-72. 被引量:33
  • 2黄河中型水电开发有限责任公司,中国水电顾问集团西北勘测设计研究院.黄河苏只水电站泄洪闸消力池无砂排水管排水带泥原因分析及治理研究报告[R].2013..

二级参考文献3

共引文献32

同被引文献16

引证文献4

二级引证文献6