一类零缓冲可中断流水线调度优化方法 被引量:1

An Optimization Method for Scheduling a Zero-Buffer and Interruptible Flow Line
下载PDF
导出
摘要 针对具有多种平面分段的流水线调度中存在的拖期、流水线闲置和生产效率低等问题,构建零缓冲可中断流水线的调度模型。以分段总完工时间最短及最小延期交货惩罚为目标,同时考虑分段的排序、流水线选择情况,利用运筹学方法建立平面分段流水线调度问题的非线性整数规划模型。在此基础上,结合某船厂实际数据通过实验验证了模型的有效性。将该优化模型调度结果与SPT、EDD、WSPT、FCFS四种调度规则下的结果进行对比,结果表明:该优化模型调度得到的总完工时间最短,且延期交货惩罚最小。 A zero-buffer and interruptible flow line scheduling model is built to respond to the tardiness , i-dleness and low efficiency of the panel block flow line scheduling problem .Taking the shortest makespan and minimum punishment of delivery extension as the objective and considering the sequence , line selection, a nonlinear integer programming for this scheduling problem is proposed .On this basis , experiment results with the actual data of a shipyard demonstrate the effectiveness of the model .Comparing the sched-uling results of the optimized model with the other four scheduling rules ( SPT, EDD, WSPT, FCFS) , it is found that the makespan is shortest and the punishment of delivery extension minimum .
出处 《工业工程》 北大核心 2014年第5期1-9,共9页 Industrial Engineering Journal
基金 国家自然科学基金资助项目(71071107)
关键词 流水线 平面分段 完工时间 整数规划 调度 flow line panel block makespan integer programming scheduling
  • 相关文献

参考文献21

  • 1Quadt D, Kuhn H. Batch scheduling of jobs with identical process times on flexible flow lines [ J ]. International Journal of Production Economics, 2007, 105 (2) :385-401.
  • 2Chen C L. A bottleneck-based heuristic for minimizing makespan in a flexible flow line with unrelated parallel ma- chines[ J]. Computers & Operations Research, 2009, 36 ( 11 ) :3073-3081.
  • 3Sawik T. An Exact Approach for Batch Scheduling in Flexi- ble Flow Lines with Limited Intermediate Buffers[J]. Mathe- matical and Computer Modeling, 2002, 36 (4-5) :461-471.
  • 4Zandieh M, Fatemi Ghomi S M T, Moattar Husseini S M. An immune algorithm approach to hybrid flow shops schedu- ling with sequence-dependent setup times [ J ]. Applied Mathematics and Computation, 2006, 180 ( 1 ) : 111-127.
  • 5Yagmahan B, Yenisey M M. Ant colony optimization for multi-objective flowshop scheduling problem [ J ]. Computers &Industrial Engineering, 2008, 54 ( 3 ) :411-420.
  • 6Alexandros D C, Chrissoleon P T. Exact analysis of a two- workstation one-buffer flow line with parallel unreliable ma- chines [ J ]. European Journal of Operational Research, 2009, 197(2) :572-580.
  • 7Scholl A, Boysen N, Fliedner M. The assembly line balan- cing and scheduling problem with sequence-dependent setup times: problem extension, model formulation and efficient heuristics [J]. OR Spectrum, 2013, 35( 1 ) : 291-320.
  • 8Yagmahan B. Mixed-model assembly line balancing using a multi-objective ant colony optimization approach [ J]. Expert Systems with Aoolications, 2011, 38(10) : 12453-12461.
  • 9王凌,周刚,许烨,金以慧.混合流水线调度研究进展[J].化工自动化及仪表,2011,38(1):1-8. 被引量:27
  • 10Bouabda R, Jarboui B, Eddaly M, Rebai A. A branch and bound enhanced genetic algorithm for scheduling a flowline manufacturing cell with sequence dependent family setup times [ J ]. Computers& Operations Research, 2011, 38 ( 1 ) :387-393.

二级参考文献141

  • 1张宏远,席裕庚,谷寒雨.A Decomposition and Coordination Scheduling Method for Flow-shop Problem Based on TOC[J].自动化学报,2005,31(2):182-187. 被引量:7
  • 2轩华,唐立新.实时无等待HFS调度的一种拉格朗日松弛算法[J].控制与决策,2006,21(4):376-380. 被引量:25
  • 3满春涛,孙明辉,张礼勇.粒子群优化算法在多峰函数寻优上的应用[J].哈尔滨理工大学学报,2007,12(2):11-13. 被引量:6
  • 4LEE K J, LEE J K,CHOI S Y. A spatial scheduling system and its application to shipbuilding : DAS-CURVE [ J ]. Expert Systems with Applications, 1996,10 ( 3/4 ) : 311-324.
  • 5RAJ P. Solving spatial scheduling problem: an analytical approach[ C ]//Proceedings of the 37th International Conference on Computers and Industrial Engineering. Alexandria, Egypt, 2007:2002-2011.
  • 6ZHENG Junli, JIANG Zhibin. Minimizing makespan at module assembly shop in shipbuilding[ C ]//Proceedings of 2008 IEEE International Conference on Service Operations and Logistics, and Informatics. Beijing, China, 2008: 1794-1799.
  • 7MIN S G, LEE M W. A genetic algorithm application for the load balancing of ship erection process [J]. IE Interfaces, 2000,13 ( 2 ) : 225-233.
  • 8LI Bo, ZHAO Z Y. A dynamic scheduling method for spatial layout planning [ C ]// Proceedings of the Fourth International Conference on Machine Learning and Cybernetics. Guangzhou, China, 2005:3612-3617.
  • 9EBERHART R C, KENNEDY J. A new optimizer using particles swarm theory [ C ]//Proceedings 6th International Symposium on Micro Machine and Human Science. Nagoya, Japan, 1995:39-43.
  • 10SHI Y, EBERHART R C. A modified particle swarm optimizer [ C ]//Proc of the IEEE Conference on Evolutionary Computation. Anchorage, USA, 1998:69-73.

共引文献60

同被引文献2

引证文献1

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部