期刊文献+

基于动车运用的高速铁路列车运行图鲁棒性研究 被引量:9

Study on Robustness of High-speed Train Working Diagram based on EMU Utilization
下载PDF
导出
摘要 基于离散事件动态系统理论,将列车发车作为基本事件,运用Max-Plus Algebra方法建立列车运行图的状态动力学方程和列车晚点传播模型;设计列车次序可调整条件下晚点传播的计算流程及方法,研究状态矩阵的更新,使Max-Plus Algebra能够适用于状态矩阵改变的迭代运算;最后综合评价列车发车次序调整、设置交路接续冗余时间及动车组交路调整3种策略对列车运行图鲁棒性的影响。案例计算结果表明,合理设置交路接续冗余时间、调整列车发车次序和调整交路能够有效消减列车晚点,提高列车运行图的鲁棒性。 Based on dynamic system theory of discrete event,taking the train departure as the basic event,the status dynamic equation of train working diagram and train delay propagation model were established by using Max-Plus Algebra,the computation process and method of delay propagation under adjustable train order were designed,and the upgrading of status equation was studied as to make Max-Plus Algebra applying to the iterated operation changed by status equation.In the end,the comprehensive evaluation on influence of 3 strategies(such as adjusting train departure order,configuring connected redundancy time of route and adjusting EMU route) on robustness of train working diagram.The example computation result shows the above 3 strategies could effectively cut down train delay and increase the robustness of train working diagram.
出处 《铁道运输与经济》 北大核心 2014年第11期50-55,共6页 Railway Transport and Economy
基金 国家自然科学基金项目(60870012) "十一五"国家科技支撑计划项目(2009BAG12A10) 中国铁路总公司科技项目(2013X014-C)
关键词 列车运行图 Max-Plus ALGEBRA 鲁棒性 晚点传播 列车运行调整 Train Working Diagram Max-Plus Algebra Robustness Delay Propagation Train Operation Adjustment
  • 相关文献

参考文献8

二级参考文献44

共引文献78

同被引文献51

引证文献9

二级引证文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部