摘要
建设工程的竣工结算,是确定工程造价的必要程序和重要手段,也是控制投资的最终环节。如何遵照合法、平等、诚信的原则,正确处理征地拆迁、签证及价差调整中存在的有关问题,此文依据政策文件、承发包合同约定和相关协议及交易习惯进行探讨,并提出方法和建议。以求达到维护国家利益和合同双方当事人的合法权益。
The construction project completion settlement is the necessary program and important means to determine the project cost and the final link to control investment. The policy document, contracting contract and relevant agreement and trading habits were discussed and the methods and suggestions of how to correctly handle the cost problems of the land requisition and demolishing, visa and price difference according to the principles of legal, equality and good faith were put forward, In order to safeguard national interests and the lawful rights and interests of the contract parties.
出处
《铁路工程造价管理》
2014年第6期20-23,共4页
Railway Engineering Cost Management
关键词
建设工程
征地拆迁
签证
价差
费用
Construction project
Land requisition and demolishing
Visa
Price difference
Cost