摘要
通过工程实例,阐述了采用分层强夯法消除高填土电厂厂区地基的湿陷性,并采用CFG桩复合地基对受水浸泡可能性大的重要建(构)物地基进行了二次处理,对CFG桩复合地基的经济性及安全性进行了研究分析,指出采用该方法取得了良好的施工效果。
Through the project example, this paper elaborated using the stratified compaction method to eliminate the collapsible of high fill soil power plant foundation, and using CFG pile composite foundation made secondary treatment to important constructs foundation immersion by big possibility water, and analyzed the economy and safety of CFG pile composite foundation, pointed out that the using this method gained good con- struction effect.
出处
《山西建筑》
2014年第36期67-68,共2页
Shanxi Architecture
关键词
地基
强夯
CFG桩
承载力特征值
沉降
foundation, dynamic compaction, CFG pile, hearing capacity characteristic value, settlement