摘要
介绍了浙江天台山风电场的区位优势,对风力发电机的选型和布置进行了研究,探讨了电气与土建设计方式,研究了风电机组的运输与安装方法,并针对风电场运行出现的问题提出了改进对策,指出经过改进维护,全部风机进入正常运行发电状态。
This paper introduced the location advantages of Zhejiang Tiantai Mountain wind power station, researched the type selection and lay- out of wind power generator, explored the electrical and civil engineering design way, researched the transportation and installation method of wind turbines, and put forward improvement countermeasures according to the appeared problems of wind power station operation, pointed out that after the improvement and maintenance, all the wind turbines into the normal power operation.
出处
《山西建筑》
2014年第36期121-123,共3页
Shanxi Architecture
关键词
风电场
设计
风力
电气
运输
塔架
wind power station, design, wind, electrical, transportation, tower