摘要 新元矿井建井初期采用立井开拓方式,立井到底后,如仍采用地面通风,仅能满足4个掘进工作面的用风需求。为满足安全高效的施工要求,通过分析比较两种通风方案,选择在中央进、回风井井筒安装4趟玻璃钢风管作为假回风,实现了矿井建设期间的全负压通风,通风能力可满足15个掘进工作面生产,保证了矿井安全生产。 Adopts the pioneering way of vertical shaft mine, it can only satisfy the wind demand of four tunneling during the initial period of construction in Xinyuan coal faces using the ground ventilation. In order to satisfy the safe and efficient construction requirement, analyzes and compares the two ventilation schemes, chooses that installs four glass steel wind ducts as false return air, realizes all negative pressure ventilation during the construction period of the coal mine, delivery volume can satisfy the production of fifteen tunneling faces.
作者 王海凤
出处 《山西焦煤科技》 2014年第10期35-37,共3页 Shanxi Coking Coal Science & Technology
关键词 建井 安全高效 通风技术 Shaft building Safety Efficiency Ventilation technology
  • 相关文献

参考文献1

  • 1袁亮.煤矿总工程师技术手册[M].北京:煤炭工业出版社,2004:334—376.

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部