同工况条件下不同静载方法在抗拔桩中的技术分析 被引量:1

Technological Analysis of Different Static Load Method in the Uplift Pile Under the Same Working Condition
下载PDF
导出
摘要 在进行抗拔桩试验工程中,为了达到工程设计安全,需要进行静载荷试验,传统的锚桩法成本高,操作不方便,随着桩径、桩长的增大,其需要的反力也随之增大,而采用自平衡法进行静载荷测试,很容易增大反力,且具有操作方便、缩短工期、节省施工成本的优点,从两种工程实例得出结论,对于抗拔桩,传统锚桩法及自平衡法均可使用,但使用自平衡法效果更好。 In the uplift pile test engineering,in order to achieve safety engineering design we needed to carry on static load test,the traditional method of anchor pile cost high and its operation was not convenient,as increasing of the pile diameter and pile length the reaction has been increased. The selfbalanced method could be apt to increase the reaction,and has the advantages of convenient operation,shorten the construction period,saving construction cost. Conclusions from two engineering examples,the traditional method of anchor pile and self-balancing method all can use for the uplift pile,but using the latter is better.
出处 《工程质量》 2014年第12期78-81,共4页 Construction Quality
关键词 抗拔桩 静载荷试验 锚桩试桩法 自平衡试桩法 比较 uplift pile static load test anchored pile method the self-balanced method contrast
  • 相关文献

参考文献4

  • 1广州地质勘察基础工程公司.广州中海科学城高层住宅区勘察报告[R].2013.
  • 2广东省建筑科学研究院.DBJ15-60-2008建筑地基基础检测规范[S].北京:中国建筑工业出版社,2008.
  • 3南昌永祺科技发展有限公司.DB36/T 574-2010桩身自反力平衡荷载箱[S].北京:中国建筑工业出版社,2010.
  • 4东南大学.JT/T 738-2009基桩静载试验自平衡法[S].北京:人民交通出版社,2009.

共引文献2

同被引文献8

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部