多施工层无节奏专业流水施工组织与优化 被引量:2

On Organization and Optimization Method for Multi-storey Flowing Construction with Irregular Paces
下载PDF
导出
摘要 在介绍了无节奏专业流水施工特点的基础上,总结出多施工层无节奏专业流水工期的计算办法,注意到不同的施工段实施次序对多施工层无节奏专业流水工期的长短有着显著影响,尝试运用矩阵法寻求施工段实施的最优排列次序,实现工期最短目标。算例分析证明,在不需要增加资源投入情况下,仅调整施工段实施次序就可以实现多施工层无节奏专业流水工期优化目标。 By introducing the characteristics of flowing construction with irregular paces,this paper summarizedand put forward a working time formula of multi-storey flowing construction with irregular paces.It was noticedthat different implementation sequence of construction sections had a significant impact to working time of multi-storey flowing construction with irregular paces,and tried to find out the optimal sequence among different con-struction sections implement sequences by matrix method,finally got the shortest total working time.Case studyproved that the working time optimization can be achieved only by adjusting construction sections sequences,butnot increasing resources.
出处 《安阳工学院学报》 2014年第6期52-57,共6页 Journal of Anyang Institute of Technology
基金 安阳师范学院2014年度课程建设研究项目(编号:2014kcyj18)
关键词 多施工层 无节奏流水施工 工期 矩阵法 multi-storey construction flowing construction with irregular paces working time matrix method
  • 相关文献

参考文献4

二级参考文献16

共引文献19

同被引文献11

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部