扣件式钢管高大支模架关键构造措施的分析研究 被引量:2

Research on the Key Construction Measures of the High Supporting System Using Fastener Type Steel Pipe Falsework
下载PDF
导出
摘要 为充分把握扣件式钢管高大支模架的关键构造措施,对影响扣件式钢管模板支撑结构稳定承载力的关键构造条件进行了整架计算分析,明确了扫地杆、竖向剪刀撑、水平剪刀撑设置以及核心区域加强的构造措施对扣件式钢管高大模板支撑结构稳定承载力的影响程度.结果显示,不设置扫地杆高支模架结构非线性屈曲承载力比设置扫地杆减小约70%左右;竖向剪刀撑的设置可改变支撑结构的失稳模式,并对结构稳定承载力有大的影响;设置水平剪刀撑可以提高稳定承载力约7%~10%;设置加强核心区域可提高支撑结构稳定承载力25%~ 35%.结论指出,为了保证支撑结构的安全性,有必要明确整架关键构造措施的具体要求. In order to fully grasp the key construction measures of high supporting system using fastener style steel pipe falsework, the stability bearing capacity of the high supporting system have been analyzed considering several construction measures, such as the influences of the sweeping rod, vertical scissors bracing, horizontal scissors bracing and the core region strengthening measures. The results show that, the nonlinear buckling bearing capacity mode and bearing capaci of high supporting system without sweeping rod reduced about 70%, the instability ty can be influenced by the vertical scissors bracing settings, the stability bearing capacity can be improved about 7%-10% by the horizontal scissors bracing, and can be improved about 25%- 35% by strengthening the core area. The conclusion pointed out that, it is necessary to clear the key structural measures of the high supporting system to ensure the safety.
出处 《江苏建筑》 2014年第A01期26-31,共6页 Jiangsu Construction
关键词 扣件式钢管支模架 稳定承载力 扫地杆 剪刀撑 构造措施 steel tubular formwork stability bearing capacity sweeping rod scissors bracing construction measures
  • 相关文献

参考文献6

  • 1潘德恩,彭瑞麟.钢管脚手架支撑结构类型及破坏模式之探讨[J].建筑钢结构进展,2002,4(4):18-24. 被引量:15
  • 2关于印发《全国建筑施工安全生产形势分析报告(2007年度)》的通报[EB/OL]http:/ /www.cin.gov.cn/zcfg/jswj/gc-zl/200803.
  • 3方舟建设.2004年全国建筑施工三级以上事故统计表[EB/OL].http://www.fzpmc.com/ news/ gb/.
  • 4赵玉章,刘柯.我国模板脚手架工程安全事故的现状和对策[C]//中国建筑学会施工学术委员会模板与脚手架专业委员会2007年会论文集,2007:1-9.
  • 5王新敏.ANSYS工程结构数值分析[M].北京:清华大学出版社,2003.
  • 6陈志华,陆征然,王小盾.钢管脚手架直角扣件刚度的数值模拟分析及试验研究[J].土木工程学报,2010,43(9):100-108. 被引量:80

二级参考文献20

  • 1叶康,李国强,张彬.钢框架半刚性连接研究综述[J].结构工程师,2005,21(4):66-69. 被引量:11
  • 2袁雪霞,金伟良,鲁征,刘鑫,陈天民.扣件式钢管支模架稳定承载能力研究[J].土木工程学报,2006,39(5):43-50. 被引量:122
  • 3JGJ130-2001建筑施工扣件式钢管脚手架安全技术规范[S].北京:中国建筑工业出版社,2001.
  • 4GB15831-2006钢管脚手架扣件[S].北京:中国标准出版社,2006.
  • 5[1]Peng, J.L. Analysis Models and Design guidelines for High-Clearance Scaffold Systems. Ph.D. Dissertation, Purdue University, West Lafayette, IN., 1994, 330pp
  • 6[18]Peng, J.L., Pan, A.D.E., and Chan, S.L., 1998.11-12,Simplified Models for Analysis and Design of Modular Falsework, Journal of Constructional Steel Research, Vol. 48,No. 2/3, pp. 189-209
  • 7[19]Peng, J.L., Rosowsky, D.V., Pan, A.D.E., Chen, W.F., and Chan, S.L., 1998.04, Simplified Modeling and Analysis of Pattern Loading Effects on Shoring Systems During Construction, Advances in Structural Engineering, Vol. 1, No.3, pp.203-218
  • 8[20]Peng, J.L., Pan, A.D.E., Chen, W.F., Yen, T., and Chan, S.L.,1997.09, Structural Modeling and Analysis of Modular Falsework Systems, ASCE Journal of Structural Engineering,Vol. 123, No. 9, pp. 1245-1251
  • 9[21]Peng, J.L., Yen, T., Lin, I., Wu, K.L., and Chen, W.F.,1997.06, Performance of Scaffold Frame Shoring Under Pattern Loads and Load Paths, ASCE Construction Engineering and Management Journal, Vol. 123, No. 2,pp.138-145
  • 10[22]Peng, J.L., Rosowsky, D.V., Pan, A.D., Chen, W.F., and Yen,T., 1996.03-04, Analysis of Concrete Placement Load Effects Using Influence Surfaces, ACI Structural Journal, V. 93, No. 2,pp.180-186

共引文献93

同被引文献21

  • 1中华人民共和国住房和城乡建设部.JGJ162-2008建筑施工模板安全技术规范[s].北京:中国建筑工业出版社,2008.
  • 2中华人民共和国住房和城乡建设部.JGJ130-2011建筑施工扣件式钢管脚手架安全技术规范[S].北京:中国建筑工业出版社,2011.
  • 3Chandrangsu T, Rasmussen K J R. Investiga- tion of geometric imperfections and joint stiff- ness of support scaffold systems [ J ]. Journal of Constructional Steel Research, 2011,67 (4) : 576 - 584.
  • 4Liu Li, Wang Bo, Wang Juchao. Analysis on impact of the node connection pattern for fas- tener-style steel pipe formwork support [ J ]. Applied Mechanics and Materials, 2014 ( 580/ 583 ) :2224 - 2227.
  • 5Liu Li,Wang Bo ,Liu Yanan. AnaLysis on later- al deformation of high-formwork in different column's spacing of bridging[ J]. Applied Me- chanics and Materials, 2014 ( 580/583 ) : 2228 - 2231.
  • 6Liu Li, Wang Juchao, Wang Bo. Research on influence of concrete pouring sequence on sta- bility of high-formwork support system [ J ]. Applied Mechanics and Materials, 2014 ( 580/ 583) :2235 - 2238.
  • 7Liu Li, Liu Yanan, Wang Bo. Influence of bridging arrangement location on the mechani- cal characteristics of the high-forrnwork support system [ J ]. Applied Mechanics and Materials, 2014(580/583 ) :2232 - 2234.
  • 8Liu Li, Wang Fang, Wang Juchao. Influence of concrete pouring sequence on stability of differ- ent height high-forrnwork support system [ J ]. Advanced Materials Research, 2014 ( 838 ) : 227 - 230.
  • 9Serge T, Jens V D M, Niels V, et al. Numerical simulation of formwork pressure while pum- ping self-compacting concrete bottom-up [J]. Engineering Structures,2014(70) :218 -233.
  • 10Taehoon K, Hyunsu L, Ung-Kyun L, et al. Ad- vanced formwork method integrated with a lay- out planning model for tall building construc- tion[ J ]. Canadian Journal of Civil Engineer- ing,2012,39(11) :1173 - 1183.

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部