摘要
广渠路跨丰双铁路分离式立交桥连续2跨跨越电气化繁忙铁路,为把对既有线路正常运营的影响降到最低,确保施工期间的行车安全,项目采用顶推法施工。结合项目特点,通过对施工过程关键点的介绍以及对监控内容和方法的探讨,为今后类似工程的施工提供现场施工经验。
The separate overpass of Guangqu Road overcrossing Fengshuang Railway goes over two electrified busy railway in a row.To reduce the effect on the normal operation of existing routes as much as possible,the project adopts the incre-mental launching method to ensure the safety during construction.According to the features of the project,the key points in construction process are introduced and the study is made on the monitoring content and method,which provide field con-struction experience for the future similar engineering.
出处
《铁道建筑技术》
2014年第11期4-7,共4页
Railway Construction Technology
关键词
跨铁路
钢箱梁
顶推法
监控技术
overcrossing railway
steel box girder
incremental launching method
monitoring technology