摘要 随着我国电网信息化水平的提高,全寿命周期设计建设管理将在变电站设备管理领域发挥越来越重要的作用。系统分析了变电站专业管理的指标体系及目标值和主要措施,并对变电站全寿命周期设计建设管理进行了全面的设计优化。在编制变电站设备技术规范过程中,对设备提出寿命管理,建立了产品重大质量问题厂家负责返厂修复的"召回"制度,从而实现了变电站资产全寿命周期成本最优化的目标。 With the development of the level of the information, the life cycle construction and management of the transformer substation have been paid more and more attention to. The target system and the target value of the transformer substation management and the major measures are analyzed and the life cycle construction and manage- ment of the transformer substation has a comprehensive design optimization. Additionally, in the preparation of sub- station equipment specification, the management of the LCC has been proposed and set up "recall" system for a- chieving optimum management of the LCC of the transformer substation.
出处 《电力科学与工程》 2014年第12期68-72,共5页 Electric Power Science and Engineering
关键词 变电站 全寿命周期管理 最优目标 经验分析 transformer substation life cycle management optimum goals empirical analysis
  • 相关文献

参考文献12

二级参考文献69

共引文献222

同被引文献17

  • 1SOLOMON R, SANDBORN P A, PECHT M G. Elec- tronic part life cycle concepts and obsolescence forecas- ting [J]. IEEE Transactions on Components & Packa- ging Technologies, 2001, 23 (4) : 707 -717.
  • 2ASIEDU Y, Gu P. Product life cycle cost analysis: State of the art review [ J]. International Journal of Production Research, 2010, 36 (4) : 883 -908.
  • 3CANOVA A, PROFUMO F, TARTAGLIA M. LCC de- sign criteria in electrical plants oriented to the energy saving [ J ]. IEEE Transactions on Industry Applica- tions, 2001, 2 (1): 53-58.
  • 4NIWA M, KATO T, SUZUOKI Y. Life - cycle - cost e- valuation of degradation diagnosis for cables [ C] //E- lectrical Insulating Materials, 2005. (ISEIM 2005 ). Proceedings of 2005 International Symposium on. IEEE, 2005, (3): 737-740.
  • 5JEROMIN I, BALZER G, BACKES J, et al. Life cycle cost analysis of transmission and distribution systems [ C ] //PowerTech, 2009 IEEE Bucharest. IEEE, 2009 : 1 - 6.
  • 6NILSSON J, BERTLING U. Maintenance management of wind power systems using condition monitoring sys- tems [ CI // Power Engineering Society General Meet- ing, 2007. IEEE. IEEE, 2007: 1 - 1.
  • 7RODRIGUEZ G A R, O'NEILL-CARRILLO E. Eco- nomic assessment of distributed generation using life cy- cle costs and environmental externalities [ C] // Power Symposium, 2005. Proceedings of the 37th Annual North American. 2005 : 412 -420.
  • 8马仲能,钟立华,卢锴,夏成军.基于电力设备全寿命周期成本最优的检修策略研究[J].电力系统保护与控制,2011,39(16):34-39. 被引量:56
  • 9LIU Lu CHENG Haozhong MA Zeliang YAO Liangzhong BAZARGAN Masoud.Multi-objective Transmission Expansion Planning Considering Life Cycle Cost[J].中国电机工程学报,2012,32(22). 被引量:31
  • 10沈广,苏海锋,袁喆.基于全寿命周期安全效能成本的配网规划方案评价研究[J].华东电力,2013,41(1):131-135. 被引量:13

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部