摘要
藏木水电站高线供料平台位于右岸坝肩3 313.75 m高程,依附右岸坝顶公路,受料平台所处边坡陡峭,采用常规的混凝土结构或钢结构,施工难度大,成本高。为此,结合现场实际地形,优化设计,采用三脚架做支撑,锚杆混凝土支墩做基座,充分利用了钢结构制作工艺简单、安装、拆除便利等特点。成功解决了缆机供料平台支撑以及加固困难的问题,具有很大的实用性,值得同类工程借鉴。
The high material feeding platform of ZangMu Hydropower Project was arranged on the right dam abut-ment at EL.3313.75 m,and was attached to the right crest road. The material receiving platform was located by steep slope. Conventional concrete or steel structures may lead to much construction difficulties and high costs. Therefore,design was optimized combined with actual landform. Steel structures permit simple fabrication tech-nique,convenient assembly and dismantle. The design made full use of these advantages with tripod supports and anchor concrete base being adopted,which solve the supporting and reinforcing problem of cable machine feeding platform. It is a practical scheme and may be reference for similar project.
出处
《广西水利水电》
2014年第6期34-37,共4页
Guangxi Water Resources & Hydropower Engineering
关键词
藏木水电站
供料平台
设计
ZangMu Hydropower Project
material feeding platform
design