摘要
介绍了印尼巴厘岛燃煤电厂项目的基本概况,核实了主变压器变比技术参数,发现了印尼国家电力公司提出的主变压器变比技术要求存在诸多矛盾,计算了主变压器变比,在与印尼国家电力公司进行了技术沟通后,修改了变压器技术参数的要求。
The general situation of the Indonesia Bali Island Coal-fired Power Plant was introduced. The technical parameters about the main transformer ratio were checked. It was found thatthere were some contradictions in the main transformer ratio technical requirement proposed by Indonesia National Electric Power Company. The ratio of the main transformer was calculated. Aiming at above problem,the project contractor communicated with Indonesia National Electric Power Company,and the requirement of technical parameters of the main transformer was amended.
出处
《华电技术》
CAS
2014年第12期32-34,37,共4页
HUADIAN TECHNOLOGY
关键词
巴厘岛燃煤电厂
主变压器
变比
调压开关
Bali Island coal-fired power plant
main transformer
ratio
tap changer