摘要
介绍组合式打桩船在柬埔寨优联码头钢管桩施工中的应用,重点介绍打桩船设计、组装及工程应用效果。经对钢管桩实际桩位测量后发现桩位偏差全部合格,组合式打桩船可以适应类似水域的施工要求。
This paper describes the application of modular piling ship in the Cambodia Union Port, focuses on ship design, assembling and project using effects. Through the practical steel pipe pile location measurement, the results show that the pile position deviations are all qualified, and the modular piling ship can meet the construct requirements of similar water.
出处
《中国港湾建设》
2014年第12期62-65,共4页
China Harbour Engineering
关键词
组合式
打桩船
箱体
组装
modular
piling ship
case
assembling