摘要
水电站厂房是水电站的重要组成部分,渗漏水将影响厂房的使用功能和使用寿命。本文对柳树沟水电站工程下闸蓄水后厂房出现的渗漏点进行了原因分析,指出了薄弱环节,并根据不同渗漏情况采取了相应处理方案,较好地控制了厂房的渗漏情况。
Hydropower station plant is an important part of hydropower station,and leakage water will affect use function and service life of the plant. In the paper,causes of leakage in the plant after reservoir impoundment of Liushugou Hydropower Station Project are analyzed. Weak links are pointed. Corresponding treatment plan is adopted according to different leakage conditions,and plant leakage condition is better controlled.
出处
《中国水能及电气化》
2014年第12期30-34,共5页
China Water Power & Electrification
关键词
水电站厂房
渗漏水
施工缝
处理方案
hydropower station plant leakage water construction joints treatment plan