呼和乌素煤矿特大突水事故应急处理及后续治理方案 被引量:3

Emergency and Subsequent Treatment of Ultra- large Water Inrush Accident in Hoh Us Coal Mine
下载PDF
导出
摘要 呼和乌素煤矿露天采坑因与小煤窑采空区贯通导致突水被淹,进而波及呼和乌素井工矿和临近补连塔煤矿采空区,基于此,研究采取了封堵突水点、注浆封堵突水巷道、积极排水、可控疏水降压等措施,并提出了永久解决乌兰木伦河对相关矿井影响的应对方案,保证了矿井的安全。 As Hoh Us open pit coal mine cut- through the goaf of a small mine,water inrush accident happened,and spread to Hoh Us underground mine and the adjacent goaf of Bulianta coal mine.Based on this condition,water inrush point was blocked,water inrush roadway was sealed with grouting,water drainage and controllable water pumping and pressure releasing were conducted,ensuring the coal mine safety.And the permanent solution for coal mine water problems caused by Ulan Moron River.
出处 《煤炭工程》 北大核心 2015年第1期71-73,共3页 Coal Engineering
关键词 特大突水事故 老空水害 小煤窑 注浆封堵 排水 可控疏水降压 ultra-large water inrush accident water hazard in old goaf small mines grouting seal water drainage controllable water pumping and pressure releasing
  • 相关文献

参考文献8

二级参考文献52

共引文献219

同被引文献39

引证文献3

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部