高重型地连墙钢筋笼双机抬吊施工技术

Double-machine Hoisting Construction Technology of High Heavy Diaphragm Wall Steel Reinforced Cage
下载PDF
导出
摘要 目前国内轨道交通车站和隧道施工大部分还是采用明挖法,基坑围护结构主要是地下连续墙支护方式。以宁波市机场快速干道永达路连接线工程I标段为实例,重点介绍了地连墙施工中高重型钢筋笼吊装的吊装参数确定、起重设备选型、吊点布置和双机抬吊过程中的施工技术控制要点。 At present, the rail traffic station and tunnel are mostly constructed by the excavation method in China. The enclosure structure of foundation pit is mainly the underground diaphragm wall for support.According to the Bid I of Ningbo Airport Expressway Yongda Road Connection Project, the article focuses introduction on the determination of hoisting parameters, selection of hoisting equipment, arrangement of hoisting points and construction technical control gist in the double-machine hoisting process of high heavy steel reinforced cage in the construction of diaphragm wall.
作者 章洪俊 金凯
出处 《城市道桥与防洪》 2014年第11期153-156,28,共4页 Urban Roads Bridges & Flood Control
关键词 地连墙 高重型钢筋笼 吊点 双机抬吊 diaphragm wall,high heavy steel reinforced cage,hoisting point,double-machine hoisting
  • 相关文献

参考文献5

  • 1王新成,何江.地铁连续墙施工中钢筋笼的吊装技术[J].铁道建筑,2003,43(4):26-27. 被引量:8
  • 2JGJ 33—2001.建筑机械使用安全技术规程[S].
  • 3宁波市政工程建设集团股份有限公司.宁波市机场快速干道永达路连接线工程I标段地连墙施工方案[R].宁波:宁波市政程建设集团股份有限公司,2013.
  • 4GB 6067—1985,起重机械安全规程[S].
  • 5JGJ 18—2003,钢筋焊接及验收规范[S].

共引文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部