复合肥造粒塔工程滑升模板施工技术

Construction Technology for Sliding Formwork in Compound Fertilizer Prilling Tower Engineering
下载PDF
导出
摘要 山东某复合肥造粒塔工程由两个直径18m的圆塔与两座方塔衔接并排组成,总高度124.5m。圆塔内在高程96m及以上有5层现浇钢筋混凝土楼板平台,中间是方塔,内设楼梯间、电梯井和斗提间。圆塔的筒壁及方塔的竖向墙体采用滑模施工。经过多座同类工程施工,仍保持施工顺序不变,但对施工工艺局部进行了改进,取得了切实可行的较好效果。 A compound fertilizer prilling tower engineering in Shandong is established by two circular towers with the diameter of 18 m and two square towers, with the total height of 124.5m. The circular tower has five layers of cast-in-place reinforced concrete floor platform at the altitude of 96 m and above, in the middle is a square tower, with internal staircases, elevator wells and bucket between. The vertical wall of circular tower and the cylinder wall of the square tower adopted sliding framework construction. After many base constructions of similar projects, the construction sequence remains unchanged, but the specific construction technology is improved with good practical results achieved.
出处 《重庆建筑》 2015年第1期44-47,共4页 Chongqing Architecture
关键词 滑升模板制作 组装 滑升 拆除 施工技术 sliding rise template fabrication assembly sliding demolition construction technology
  • 相关文献

参考文献3

  • 1中华人民共和国建设部.GB50113-2005滑动模板工程技术规范[S].北京:中国建筑工业出版社,2005.
  • 2中华人民共和国住房和城乡建设部.GB50669-2011钢筋混凝土简仓施工与质量验收规范[S].北京:中国建筑工业出版社.2011.
  • 3中华人民共和国住房和城乡建设部.GB 50666-2011混凝土结构工程施工规范[S].北京:中国建筑工业出版社,2011.

共引文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部