介绍了在刘家峡水电厂水轮发电机组制动器改造项目中,新制动器装配方法的研究实施。通过现场实际操作,最终达到了机组安装工艺要求,确保机组安全稳定运行。
The assembly technology of the brake in hydro-turbine unit is introduced, which is adopted in the renovation work of the brake in Liujiaxia Hydropower Station.Field practice shows that installation requirements for the assembly of the new brake are satisfied, which ensures the stable and safe operation of the unit.