结合LBS风电场风机基础冬季混凝土施工实例,介绍了混凝土冬季施工工艺,通过控制拌和温度、浇筑和养生温度等一系列质量控制措施,达到了预期的效果,为寒冷地区风机基础混凝土冬季施工提供了技术参考。
Techniques for concrete construction in winter that adopted in the construction of wind turbine foundation of the LBS Wind Power Station are introduced.The quality control measures include the appropriate temperature of con-crete mixing, pouring and curing.Satisfactory result is obtained with these measures, which could be a useful technical reference for winter concrete construction in cold regions.
出处
《水电与新能源》
2015年第1期74-75,78,共3页
Hydropower and New Energy
关键词
风机基础
质量控制
冬季施工
wind turbine foundation
quality control
winter construction