浅谈转换层钢筋、木工及钢结构施工工序及施工技术

Discussion on the Construction Process and Construction Technology of Reinforced Steel on the Conversion, Woodworking and Steel Structure
下载PDF
导出
摘要 本文结合佛山雄盛王府广场项目框支剪力墙结构的转换层柱及梁截面尺寸大、柱中设计有钢骨、梁柱接头位置有抗剪钢板等特点,重点介绍了转换层各工种、工序如何穿插衔接配合,从而解决了加快现场工期进度等问题。 This paper combined with the characteristics of columns of conversion layer and section size of large beam, steel support in column design shear plate at joint position of columns in the frame supported shear wal structure in Xiongsheng Palace Square project in Foshan city, mainly introduced the connection methods between the coordination processes of conversion layers, thus to speed up construction progress problems.
出处 《城市建筑》 2014年第23期71-71,96,共2页 Urbanism and Architecture
关键词 超大梁 大直径柱 钢骨柱 抗剪钢板 施工工序 super beam large diameter column steel reinforced concrete column shear plate construction process
  • 相关文献

参考文献3

  • 1GB50666-2011,混凝土结构工程施工规范[S].2011.
  • 211G101-1,混凝土结构施工图、平面整体表示方法制图规则和构造详图(现浇混凝土框架、剪力墙、梁、板)[S].
  • 3佛山雄盛王府广场综合体A地块A1区、A2区钢结构深化设计图纸[Z].

共引文献53

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部