摘要
望京SOHO-T3工程幕墙总面积达6.77万m^2,包括玻璃幕墙、铝板幕墙、铝合金百叶等。施工中针对幕墙外形变化多、单体重量大等特点,通过采取布设坐标控制网、严格控制预埋件定位、龙骨精确加工等措施,保证了多种幕墙顺利安装到位。
In Wangjing SOHO-T3 project, the total area of curtain wall is as large as 67700 m2, including glass curtain wall, aluminium plate curtain wall and aluminium alloy shutter, etc. Considering such characteristics of diversified shapes of curtain wall and large weight of single curtain wall, various measures are adopted during construction, such as setting coordinate control net, strict control on positioning of preembedded member and accurate processing of ceiling joist, etc., to guarantee smooth positioning and installation of diversified curtain walls.
出处
《建筑技术》
2014年第12期1086-1088,共3页
Architecture Technology
关键词
弧形幕墙
测量定位
幕墙安装
arched curtain wall
survey positioning
curtain wall installation