大直径深层钻孔灌注桩拔除工艺研究 被引量:6

Research on Pulling-out Technology for Long Bored Pile with Large Diameter
下载PDF
导出
摘要 结合郑州南站连接线明挖隧道(拔桩区间)拟拔桩基直径大、桩长的特点,对桩体受力特征和拔桩工艺进行了研究。通过拔桩过程中桩周土破坏模式和桩体自身的抗拉强度分析计算,选取有效的减阻方法并应用于工程实践,取得良好效果。最后总结出大直径深层钻孔灌注桩拔除工程中桩身局部扩大、桩侧摩阻力过大和断桩等问题及相应的解决方法,供今后类似工程借鉴。 According to the characteristics of long and large diameter pile to be pulled out in the open-excavated tunnel ( pile-puling interval) in Zhengzhou, the force on pile body and the pile-pulling technology are studied. Through the analysis and calculation on failure mode of soll around the pile and tensile strength of the pile body in pulling-out process, the effective method of resistance reduction is selected to be applied in the engineering practice, and good results are achieved. The solutions of pile body partial enlarged, too large pile lateral friction and pile broken in pile pulling-out operation are summed up, which can serve as reference for the same projects.
出处 《探矿工程(岩土钻掘工程)》 2015年第1期68-71,共4页 Exploration Engineering:Rock & Soil Drilling and Tunneling
关键词 钻孔灌注桩 拔桩 FCEC全回转清障机 极限侧阻力 断桩 bored pile pile pulling FCEC full rotary wrecker machine ultimate lateral resistance broken pile
  • 相关文献

参考文献12

二级参考文献35

共引文献1510

同被引文献36

引证文献6

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部