摘要
结合大唐景泰电厂一期工程2×660 MW超临界燃煤空冷机组锅炉燃烧的实际特点,深入分析锅炉排烟温度上升的原因,并提出一定的解决方案,从而实现火电厂整体效益和经济性。
Combined with the actual features of the boiler combustion of 2 × 660 MW supercritical coal-fired air-cooled units in first-stage project of Datang Jingtai Power Plant, the causes of the rise of exhaust gas temperature of boilers are analyzed in depth,and some solutions are proposed in order to achieve the overall efficiency and economy of thermal power plants.
出处
《能源与节能》
2015年第2期21-22,29,共3页
Energy and Energy Conservation