摘要
本文根据沈阳市某跨越铁路连续梁桥梁施工,对连续梁挂篮悬臂灌注梁段施工进行了分析,包括挂篮拼装、挂篮静载试验、梁段循环施工、边跨直线段施工、合龙段施工、挂篮拆除、施工各阶段线形控制要点,为广大连续梁桥梁施工一线技术人员提供参考。
According to a across railway continuous beam bridge construction in Shenyang, this paper analyzed the hanging basket cantilever casting continuous beam construction, including hanging basket assembly, hanging static contains test, beam segment cycle construction, side across line segment construction, closure segment construction, hanging basket demolition, and linear control points in each stage of the construction, providing reference for continuous beam bridges construction of the first-tier technicians.
出处
《价值工程》
2015年第10期159-160,共2页
Value Engineering
关键词
挂篮
连续梁
施工分析
hanging baskets
continuous beam
construction analysis