结合实际施工,研究一种断面定义法,利用算法及数据结构开发基于C++的桥梁钻孔桩坐标计算程序。该程序在实际工程中进行了测试,完全可行,提高了数据计算的效率和准确度。
Combined with the actual construction,a section definition method is studied,using the algorithm and data structures,a bridge borehole pile coordinate calculation program is developed based on c++.It is tested in the practical engineering. The program is completely feasible,and has improved the efficiency and accuracy of the data calculation.
出处
《河南科技》
2015年第1期112-114,共3页
Henan Science and Technology
关键词
桥梁钻孔桩坐标
断面定义
C++
算法及数据结构
效率
bridge bored pile coordinate
section definition
C + +
algorithms and data structures
efficiency