开放环境下城市高架现浇混凝土箱梁的施工策划及社会交通疏解 被引量:1

Construction Proposal for Urban Elevated In-Situ Concrete Box Girder Under Open Environment and Social Traffific Relief
下载PDF
导出
摘要 昆山市中环快速化改造工程S-1标范围内的高新区立交段面临工程路线长、体量大、组织协调要求高、场地开放、周边环境复杂等难点。结合G312国道与江浦路交叉路口不封闭施工实例,对其施工及交通疏解进行了总体阐述。通过采取分阶段翻交、利用已完成立交的支架体系合理设置门洞,在保证施工质量的同时,尽量确保既有道路的通行能力,圆满完成了施工。 The project of high-tech zone interchange section, within S-1 specified zone of Kunshan city middle ring expressway reconstruction project had many difficulties including long engineering distance, large volume, high requirements of organization and coordination, and complicated surrounding environment. This paper gives an overall introduction of construction scheme based on the open intersection construction of G312 national highway and Jiangpu road. Through phase-divided reconstruction and reasonable opening layout based on the scaffold supporting system of the existing interchange, the construction was a complete success, which ensured good construction quality and the capacity of the existing highway.
作者 吕献敏
出处 《建筑施工》 2015年第2期128-130,共3页 Building Construction
基金 上海建工集团股份有限公司重点科研项目课题 课题编号为12JCSF-01
关键词 昆山市中环快速化改造工程 高架现浇混凝土箱梁 施工策划 交通疏解 门洞设置 排架搭设 Kunshan city middle ring expressway reconstruction project elevated cast-in-place box girder construction planning traffic relief door opening setting up bent frame erection
  • 相关文献

二级参考文献5

  • 1JGJ166-2008,建筑施工碗扣式钢管脚手架安全技术规范[S].
  • 2JTJ041-2000.公路桥涵施工技术规范[S].[S].,..
  • 3黄绍金,刘陌生.装配式公路钢桥多用途使用手册[M].北京:人民交通出版社,2001.
  • 4JGJ 55-2000.普通混凝土配合比设计规程[S],2000.
  • 5吴松.预应力连续箱梁施工技术[J].山西建筑,2010,36(14):295-296. 被引量:12

共引文献9

同被引文献4

引证文献1

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部