摘要 简要介绍预应力孔道压浆作为后张法预应力连续梁施工的最后一项工作,其质量对桥梁结构的承载力、使用寿命和铁路运营的安全性有着重大影响。通过工程实例主要介绍预应力孔道压浆饱满度的检查方法和不饱满时的处理措施。结果表明,预应力孔道压浆施工属隐蔽工程,压浆饱满度不能被直观发现,施工完成后对压浆饱满度进行检查也是很有必要的,为以后的工程施工提供了一定的参考价值。 Introduce that prestressed duct grouting is the last step of post-tensioned prestressed continuous beam construction,the quality has a significant impact on the bearing capacity and the life of the bridge structure,also on the safety of rail operations. Mainly Introduce the inspection methods of prestressed duct grouting fullness and the treatment measures when is not full by engineering example. The results show that prestressed duct grouting is hidden works,part or full grouting is not be intuitive discovered,grouting plumpness check is necessary after the completion of construction,all these provide a certain reference value for future construction.
作者 刘涛
出处 《福建建筑》 2015年第2期70-72,共3页 Fujian Architecture & Construction
关键词 连续梁 预应力孔道 压浆饱满度 Continuous beam Prestressed duct Grouting plumpness
  • 相关文献

参考文献3

  • 1周样.桥梁预应力孔道压浆质量无损检测技术研究与应用[M].黑龙江:黑龙江交通科技,2013.
  • 2中华人民共和国铁道部.铁路混凝土工程施工质量验收标准[Z].北京:中国铁道出版社,2010.
  • 3中华人民共和国铁道部.铁路后张法预应力混凝土梁管道压浆技术条件[M].北京:中国铁道出版社,2008.

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部