摘要 为了实现鞍钢新2号高炉安全、快速停炉,通过采取炉顶打水、控料线、回收煤气等停炉方案,使降料面过程中各项操作参数得到了合理控制,维持了炉况的稳定顺行,顺利将料面降至炉缸风口区域以下。 In order to get safe and fast shutdown of the new No.2 blast furnace in General Ironmaking Plant of Angang Steel Co., Ltd., various technical parameters during the dropping charge level are suitably controlled by taking such measures as spraying water from the top of the furnace, controlling the stockline and recovering the gas and therefore the smooth operation of BF is kept and the charge level is lowered below the tuyere zone successfully.
出处 《鞍钢技术》 CAS 2015年第1期31-35,共5页 Angang Technology
关键词 高炉 降料面 控料线 休风 BF dropping charge level controlling stockline shutdown
  • 相关文献

参考文献3

  • 1黄泽文,王加山.韶钢7号高炉2200m^3降料面操作实践[J].炼铁,2009(4):30-32. 被引量:2
  • 2周传典.高炉炼铁技术手册[M].北京:冶金工业出版社,2002.8.
  • 3任国强,董文明,杨光涛.天钢1#高炉降料面实践[C]//2012全国炼铁生产技术会议暨炼铁学术年会文集(上),北京:中国钢铁协会,2012:947-549.