摘要 斜拉桥换索工程日益增多,换索施工与交通保畅相互制约。本文结合重庆渝合高速某桥斜拉索工程的实例,对该桥的交通组织方案进行了阐述,重点介绍了分流引导方案、强制分流点的设置方案、交通组织措施、应急预案等,特别是强制分流点的设置方案对限制超载超高车辆进入施工现场比较可行。为以后类似工程提供参考。 Cable Stayed Bridge engineering change increasing, for cable construction and ensure smooth transportation of mutual restraint.In this paper,together with examples Chongqing speed of a cable-stayed bridge project, the traffic organization bridges are described, focusing on the diversion program guide,forced diversion program point, traffic organizational measures, contingency plans, especially setting mandatory diversion program point to limit vehicles from entering the construction site overload ultrahigh more feasible. Provide a reference for future similar projects.
出处 《交通节能与环保》 2015年第1期71-75,共5页 Transport Energy Conservation & Environmental Protection
关键词 斜拉索 交通组织 强制分流点 应急预案 cable-stayed traffic organization mandatory diversion points emergency plan
  • 相关文献

参考文献2

  • 1晏国泰.重庆渝合高速某桥斜拉索更换施工组织设计[z].武汉:武汉二航路桥特种工程有限责任公司,2014.
  • 2晏国泰.重庆渝合高速某桥斜拉索更换工程交通组织方案[z].重庆.武汉二航路桥特种工程有限责任公司,2014.

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部