摘要
合肥光源进行重大升级改造(HLSⅡ)的磁铁安装准直工程要在有限的时间内对近120块各型磁铁进行安装准直调节。为了保证磁铁安装准直任务顺利完成,结合合肥光源自身特点,合理使用了多种测量仪器和软件,在元件坐标系下直接进行磁铁安装准直,极大地提高了工作效率和安装精度。在经过先后三次准直安装调节后,所有磁铁均安装准直就位,定位精度达到预定要求。
About 120 magnets would be installed and aligned in the HLSⅡ upgrade project.In order to make sure the project to be completed smoothly,according to the structure characteristics of HLSⅡ,the primary control network is measured by several different instruments and softwares.The magnets are installed and aligned in the coordinate of themselves,it benefits to the efficiency and accuracy of magnets installation and alignment.After three times installation and alignment,all magnets are properly positioned,and the accuracy meets the requirement.