期刊文献+

简述混凝土面板堆石坝趾板段的固结灌浆试验 被引量:1

Brief Description of Consolidation Grouting Experiment of Concrete Face Rockfill Dam Toe Board Section
下载PDF
导出
摘要 本文结合唐河水电站混凝土面板堆石坝段固结灌浆试验工程实例,介绍了固结灌浆试验的施工过程,对固结灌浆试验中出现的漏浆、孔距以及孔内灌浆分段等特殊情况均提出了解决方案,并以固结灌浆试验及整体固结灌浆效果对提出的方案进行了论证,旨在为类似工程提供借鉴。 In the paper,consolidation grouting experiment project example of concrete face rockfill dam section in Tanghe Hydropower Station is combined for introducing the construction process of consolidation grouting experiment.Solutions are proposed for special conditions in consolidation grouting experiment such as slurry leakage,hole pitch,grouting segmentation in holes,etc.The proposed solutions are demonstrated aiming at consolidation grouting experiment and overall consolidation grouting effect,thereby providing reference for similar projects.
作者 李国胜
出处 《中国水能及电气化》 2015年第3期1-4,共4页 China Water Power & Electrification
关键词 固结灌浆试验 唐河水电站 趾板 压水试验 波速测试 consolidation grouting experiment Tanghe Hydropower Station toe board water pressure test wave velocity test
  • 相关文献

参考文献1

  • 1DL/T5148-2012.水工建筑物水泥灌浆施工技术规范[S].2012.

共引文献28

同被引文献6

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部