某高速顶推箱涵施工技术研究 被引量:9

The Construction Technology Research of the Pushing for the New Road Pass Freeway
下载PDF
导出
摘要 本文主要是依托某工业园新东路下穿京港澳高速相交工程,根据该项目自身工程项目的特点,合理的组织相应的施工组织计划,通过该项目将理论中的计算方法运用到实际工程中去,根据工程中的实际情况,通过计算箱涵的最大的顶力来确定油顶的台数,从而能够更好的指导该项目中箱涵的制作和施工安装过程,进而根据箱涵的计算结果来确定顶推过来的施工组织方案,并且在箱涵顶进的施工过程中进行监测,严格控制施工过程中箱涵的标高和位移,保证施工安全,同时本论文给箱涵施工提供了一定的指导作用。 Based on the intersection works between Xindong Road of an industrial park and Beijing-Hongkong- Macao Highway, according to the engineering characteristics of the project, appropriate organization and corre- sponding construction implementation schedule were made. Through the project, the calculation approaches in theory was applied in the practical project. The box culvert maximum jacking pressure was calculated to deter- mine the number of oil jack so as to better guide the production and construction process of the project, culvert installation, and monitoring and control in jacking construction process, the control good construction process of deformation and culvert posture, to ensure the safety of the construction process, and the design and construction of paper pushing similar culvert orovide some guidance for the future.
作者 吴炜
出处 《贵州大学学报(自然科学版)》 2015年第1期114-118,共5页 Journal of Guizhou University:Natural Sciences
基金 贵州省教育厅自然科学研究项目(黔教合字(2012)045号)
关键词 箱涵顶推 施工安装 施工监测 culvert pushing construction and installation construction monitoring
  • 相关文献

参考文献8

二级参考文献28

共引文献76

同被引文献44

引证文献9

二级引证文献23

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部