摘要
本文基于万安水库上游主要河流控制站和出库站的来沙情况,对建库前后入、出沙量进行对比,分析建库后泥沙淤积情况;通过研究典型大断面实测资料,分析建库前后断面冲淤情况.
Based on the sediment condition of the control station of main rivers in the upstream of Wanan Reservoir and the reservoir outlet station and compared the inlet sediment with the outlet sediment before the construction of this reservoir,the sediment accumulation condition after the construction of this reservoir is analyzed.Through studying the observed data of the typical section,the scour and silting condition of this section after and before the construction of this reservoir is analyzed in this paper.
出处
《江西水利科技》
2015年第1期8-15,20,共9页
Jiangxi Hydraulic Science & Technology
关键词
泥沙淤积
分析
万安水库
Sediment accumulation
Analysis
Wanan Reservoir