峡江水利枢纽二期工程2012年施工度汛措施

The Second-stage Phase of Xiajiang Key Water-control Project 2012 Construction Action in flood season
下载PDF
导出
摘要 2012年峡江水利枢纽二期工程因船闸基础断层处理进度滞后,影响施工度汛.通过采取积极措施应对,确保了2次大洪水施工安全度汛,避免了重大损失,节点目标和总工期计划未受影响.本文对峡江水利枢纽二期工程2012年施工度汛措施进行了介绍,为今后类似情况作参考. Xiajiang Key Water-control Project in 2012 is at the construction peak, but the progress of the second-stage phase lagged due to the processing of ship lock base fault affects construction and flood prevention. By taking positive action, we ensured the construction safety in the great flood season twice and avoided significant loss. The goal of node and the total time limit for project is not affected. This article introduces the action of 2012 second stage of Xiajiang Key Water-control Project construction action in flood season.
作者 朱爱如
出处 《江西水利科技》 2015年第1期74-77,共4页 Jiangxi Hydraulic Science & Technology
关键词 施工 安全度汛 二期工程 峡江水利枢纽工程 Construction safety in flood season second-stage phase Xiajiang Key Water-control Project
  • 相关文献

参考文献3

  • 1罗少桢,等.江西省峡江水利枢纽船闸闸室工程设计方案变更报告[R].南昌:江西省水利规划设计院.2011.
  • 2邓彪,等.江西省峡江水利枢纽工程二期导流方式调整方案[R].南昌:江西省水利规划设计院,2011.
  • 3朱爱如,等.江西省峡江水利枢纽工程2012年防洪度汛方案[R].南昌:江西省峡江水利枢纽工程管理局.2012.

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部