2012年峡江水利枢纽二期工程因船闸基础断层处理进度滞后,影响施工度汛.通过采取积极措施应对,确保了2次大洪水施工安全度汛,避免了重大损失,节点目标和总工期计划未受影响.本文对峡江水利枢纽二期工程2012年施工度汛措施进行了介绍,为今后类似情况作参考.
Xiajiang Key Water-control Project in 2012 is at the construction peak, but the progress of the second-stage phase lagged due to the processing of ship lock base fault affects construction and flood prevention. By taking positive action, we ensured the construction safety in the great flood season twice and avoided significant loss. The goal of node and the total time limit for project is not affected. This article introduces the action of 2012 second stage of Xiajiang Key Water-control Project construction action in flood season.