摘要
本课题是针对厂区内跨厂房大件产品(纵梁)按需、按序配送的综合改善项目。应用IE工具系统分析,以流程分析、作业过程时间构成测定、节拍测定、作业过程观测为依据,从配送作业、计划排产、生产管控、库存管理等方面改善,提升纵梁保障能力,达到后工序配送节拍要求,实际效果明显。
This topic is cross-plant bulky products (stringer) demand for the plant in the region, a comprehensive improvement projects sequential distribution. IE Tools application system analysis, process analysis, process time jobs constitute measured tempo determination based on job observation process, from distribution operations, planning and scheduling production, improve production control, inventory management, etc., to enhance the ability to protect stringers, after reaching beat distribution process requirements, the actual effect is obvious.
出处
《汽车实用技术》
2015年第3期108-110,共3页
Automobile Applied Technology