西南某岩溶山区大面积挖方工程确定土石比方法研究

Study on Method Determining Soil-Rock Ratio in Large-area Excavation Works in Southwest Karst Mountains
下载PDF
导出
摘要 在分析、总结西南岩溶地区挖方工程土石比确定方法的基础上,结合西南某岩溶山区大面积挖方工程,系统地研究了岩溶山区土石比的确定、计算方法以及精度的影响因素,提出了岩溶山区大面积挖方工程确定土石比的方法和工作程序。工程实践证明,按此方法和程序,获得的土石比精度高,可推广使用。 Based on analysis and summarization of method determining soil-rock ratio in excavation works in southwest karst mountains,the determination and calculation methods thereof and the factors affecting the accuracy,in relation to the certain large-area works there, were studied systematically, and the specific method and procedure were proposed. Through practice,the method and procedure were proved to achieve high accuracy on soil-rock ratio,and then may be used extensively.
出处 《路基工程》 2015年第2期1-5,12,共6页 Subgrade Engineering
关键词 岩溶山区 挖方工程 地貌特征 土石比 确定方法 计算方法 karst mountains excavation works geomorphic feature soil-rock ratio determination method calculation method
  • 相关文献

参考文献7

二级参考文献16

共引文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部