连续梁0号块临时固结施工技术 被引量:3

Temporary Rigid Fixity Construction Technology of 0 Block Continuous Beam
下载PDF
导出
摘要 改建铁路宁启线扬州至海安段复线电气化改造工程新三阳河特大桥(40+72+40)m连续梁跨越新三阳河。连续梁主墩位于河道中,且连续梁纵向中心线与主墩纵向中心线存在15°夹角,临时固结体系如何设置是本桥0号块施工的一项重要内容,更是0号块施工的关键工序之一。本文主要介绍墩梁斜交情况下连续梁0号块临时固结体系设计、结构验算以及施工注意事项,可为同类桥梁结构提供有益的参考。 Rebuilding the continuous beam of Xinsanyang super-large bridge(40 +72 +40)m of the double line electrification reconstruction project in Yangzhou to Haian section of Ningqi Line to span Xinsanyang River.The main piers of continuous beam is located in the river,and there is a 15° angle between the longitudinal center line of continuous beam and the longitudinal center line of main pier.How to set up temporary rigid fixity system is an important content in 0 block construction of the bridge and it's also one of the key working procedures of 0 block construction.This paper mainly introduces the temporary rigid fixity system design,structure calculation and construction points for attention of 0 block continuous beam in the condition of pier beam oblique to provide beneficial reference for the similar bridge construction.
作者 刘伯洋
出处 《价值工程》 2015年第14期93-97,共5页 Value Engineering
关键词 连续梁 0号块 斜交 临时固结 continuous beam 0 block heterotropic temporary rigid fixity
  • 相关文献

参考文献3

  • 1TB10002.3-2005-铁路桥涵钢筋混凝土和预应力混凝土结构设计规范[s].2005.
  • 2TZ324—2010,铁路预应力混凝土连续梁(刚构)悬臂浇筑施工技术指南[S].
  • 3GB50010--2010混凝土结构设计规范[S].

共引文献1415

同被引文献16

引证文献3

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部