通过分析经岸转驳船-船直取的特点,论述了其直取方式的3种工艺流程,并结合江苏省镇江市某煤炭储运码头工程的建设要求,研究了该工程两方案直取工艺方式和设备的布置形式,通过三方面的比较得到了推荐方案。
Through an analysis on the characteristic of ship-to-ship direct unloading in shore by transfer,this paper discusses three kinds of direct unloading processes,and then focuses on those two direct unloading process modes and the equipment layouts based on a wharf engineering construction requirement from a coal storage terminal in Zhenjiang city,Jiangsu province.By a comparison from three aspects,the recommended plan is obtained.
出处
《港口装卸》
2015年第2期24-28,共5页
Port Operation
关键词
经岸转驳
船-船直取
装卸工艺
皮带机
三通漏斗
shore by transfer
ship-to-ship direct unloading
handling process
belt conveyor