介绍了灯泡贯流机组轴系的安装过程,调整方法,盘车方法,质量要求以及主轴调整与导轴承间隙的关系,并通过安装工艺解决了轴系承受载荷后出现的一系列问题。
Installation procedure, adjustment method, turning method, quality require- ments, and relation between main shaft adjustment and guide bearing clearances of the bulb tu- bular unit shaft system are introduced in this paper, and a range of issues occurred in shaft sys- tem with load are solved through installation technology.
出处
《防爆电机》
2015年第2期46-49,共4页
Explosion-proof Electric Machine
关键词
灯泡贯流式机组
轴系安装
轴系调整
机组盘车
Bulb tubular unit
installation of shaft system
adjustment of shaft system
turning of unit