摘要
莱钢能源动力厂银前1#机组性能与高炉冶炼工况不匹配,为确保高炉正常稳定生产,通过对防喘系统控制程序优化改造,提高1#机组性能同时节约了生产成本。
The performance of the Yingqian No.1 generator unit of Laiwu Steel's power plant did not match the operation conditions of the blast furnaces. In order to ensure normal and stable production of the blast furnaces, through optimizing transformation of the control program for the anti-surge system the performance of No.1 generator unit was improved and production cost reduced.
出处
《冶金动力》
2015年第6期39-41,共3页
Metallurgical Power
关键词
高炉
风机工况
改造
blast furnace
condition of the blower
transformation