大岗山水电站拱坝坝肩岩体加固效果分析 被引量:1

Analysis on Reinforcing Effects of Rockmass in Arch Dam Abutment,Dagangshan Hydropower Project
下载PDF
导出
摘要 大岗山水电站坝址具备修建高拱坝的优越地形条件,但坝址区地质构造复杂,岩脉、挤压破碎带、断层和节理裂隙发育,必须进行加固处理。利用ANSYS有限元分析软件,分别对大岗山拱坝坝肩天然地基和加固地基进行了数值分析。结果表明:天然地基条件下,超载安全系数为4.0~5.0,加固地基条件下,超载安全系数为5.0~6.0。说明加固方案能够有效提高坝体的稳定性和安全度,并且明显改善坝体应变及坝体的塑性变化范围,为工程设计和施工以及类似工程加固提供了科学依据。 The dam site of Dagangshan Hydropower Project is with the superior geographic advantage of building high arch dam.But the geological tectonics her is complicated.Dike, fractured zone because of extrusion, faults and joint fissures shall be reinforced.By appli-cation of ANSYS, the value analysis is respectively performed on the natural foundation and the reinforced foundation in abutment of the Dagangshan arch dam.The analysis shows that the safety factor is 4.0~5.0 in condition of the natural foundation;5.0~6.0 in condition of the reinforced foundation.This presents that the reinforcement scheme can effectively increase stability and safety of the dam body as well as obviously improve strain and plastic variation range of the dam body, providing design, construction and similar project reinforce-ment with reference.
作者 肖薇
出处 《西北水电》 2015年第2期44-47,共4页 Northwest Hydropower
关键词 大岗山水电站 坝肩稳定 天然地基 加固地基 加固效果 分析 Dagangshan Hydropower Station abutment stability natural foundation reinforce foundation reinforcing effect analysis
  • 相关文献

参考文献4

二级参考文献26

  • 1章青,陈爱玖,王大伟.基于非线性有限元法的高拱坝坝肩岩体抗滑稳定分析[J].水利学报,2007,38(S1):84-87. 被引量:3
  • 2张林,刘小强,陈建叶,胡成秋.复杂地质条件下拱坝坝肩稳定地质力学模型试验研究[J].四川大学学报(工程科学版),2004,36(6):1-5. 被引量:26
  • 3周维垣,杨若琼,刘耀儒,林鹏.高拱坝整体稳定地质力学模型试验研究[J].水力发电学报,2005,24(1):53-58. 被引量:56
  • 4汪树玉,刘国华,魏文凯,孙兆铭.拱坝非线性全过程分析与混合线型优化[J].水力发电,1996,23(9):19-22. 被引量:6
  • 5[7]LIN J,FENG X T,DING X L,et al.Stability assessment of the Three Gorges Dam foundation,China,using physical and numerical modeling-part Ⅰ:physical model tests[J].International Journal of Rock Mechanics and Mining Sciences,2003,40(2):609-631.
  • 6[8]LIU X Q,ZHANG L,CHEN J Y,et al.Geomechanical model test study on stability of concrete arch dam[C]//MARTIN W,REN Q W,JOHN S Y ed.Proceedings of the 4th International Conference on Dam Engineering.London:A.A.Balkema,2004:557-562.
  • 7[9]CHENY,ZHANGL,HEXS,et al.Evaluation of model similarity of induced joints in a high RCC arch dam[C]//Physical Modelling in Geotechnics-6th ICPMG.[S.L.]:[s.N.],2006:413-417.
  • 8[10]HE X S,ZHANG L,CHEN Y,et al.Stability study of abutment of Jinping-Ⅰ arch dam by geomechanical model test[C]// Physical Modelling in Geotechnics-6th ICPMG.[S.l.]:[s.n.],2006:419-423.
  • 9[14]ZHANG L,LI C G,CHEN X,et al.Application of new modelling technique in Pudding,Shapai RCC arch dam[C]// International Symposium on Roller Compacted Concrete Dam,APR.[S.l.]:[s.n.],1999:578-582.
  • 10DL/T5346-2006混凝土拱坝设计规范[S].北京:中国电力出版社,2007.

共引文献90

同被引文献7

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部